Turkija – Kanalizacijos vamzdynų klojimo darbai – Rize nuotekų surinkimo sistemos statyba (2 dalis) - Baigiamieji darbai
Turkija – Kanalizacijos vamzdynų klojimo darbai – Rize nuotekų surinkimo sistemos statyba (2 dalis) - Baigiamieji darbai
I dalis: Perkančioji organizacija
I.1) Pavadinimas ir adresai:
Oficialus
pavadinimas: Department of Project Implementation (DoPI), General Directorate of European Union and Foreign Relations (DGEUFR), Ministry of Environment, Urbanization and Climate Change (MoEUCC)
Adresas: Mustafa Kemal Mahallesi 2082. Cadde No:52 Çankaya
Miestas: Ankara
Pašto
kodas: 06530
Šalis: Turkija
Asmuo
ryšiams:
El-paštas: abyd.ihale@csb.gov.tr
Interneto adresas (-ai):
Pagrindinis adresas: http://ipa.csb.gov.tr
II dalis: Objektas
II.1.1) Pavadinimas:
Construction of Rize Wastewater Collection System (Lot 2) - Completion Works
Nuorodos numeris: EC-ENEST/ANK/2026/EA-LOP/0001-PIN
II.1.2) Pagrindinis BVPŽ kodas:
45232400
Kanalizacijos vamzdynų klojimo darbai
II.1.3) Sutarties tipas:
Kita
II.1.4) Trumpas aprašymas:
The scope of work is summarised as bellow:
a) Construction of approximately 3.039 km wastewater collector pipeline, including ground
improvement works,
b) Construction of approximately 30 m Special Crossing of river by pipejacking and/or
horizontal drilling wastewater collector pipeline,
c) Construction of 3 prefabricated GRP (Glass Reinforced Plastic) Package Type
Wastewater Pumping Station (Bağdatlı, Çiftekavak and Hal)
d) Approximately 12 m forced mains and associated structures,
e) Construction of approximately 87 manholes, including relevant ground improvement
works
f) Installation of complementary SCADA System which is composed of operator
workstation system, SCADA software and licences, other relevant software and licences,
and system accessories
g) Preparation of wastewater collection system network as-built plans for constructed sewer
mains,
h) Complementary works and documentation, including:
1. CCTV inspection for approximately 6,920 m installed pipes,
2. Leakage test for approximately 963 m installed pipes,
3. Leakage test for approximately 44 manholes,
4. Completion of non-completed bridge crossing works,
5. Correction of non-conformities,
6. Provision of Certificate of Origin in accordance with Sub-Clause 7.9,
7. Preparation and submission of as-built plans for completed works.
The design for the wastewater collection system involves, in most cases, the complete
replacement of the existing pipelines. As these existing pipelines are “live” the Contractor shall
need to carefully plan the works to maintain wastewater collection services to customers as much
as possible. This issue shall be valid for all “live” wastewater pumping stations. During this
planning, the service continuity should be in the first priority. System temporary rearrangements
to be done for service continuity shall be taking into consideration during pricing. In wastewater
collection system, package wastewater pumping station shall be supplied and installed during the
construction of new one. These facilities shall be in operation until the final acceptance.
II.2) Aprašymas:
II.2.1) Kitas (-i) šio pirkimo BVPŽ kodas (-ai):
45232400 Kanalizacijos vamzdynų klojimo darbai